Due to the effects of COVID-19 on the current market and the decline in demand of new vehicles globally, Toyota intends to make gradual adjustments in production operations at all plants for completed vehicles in Japan, starting from May 1.

Specifically, we have decided to halt production for two days, on May 1 and 11, and plan to reflect the operation days on alternative dates. Additionally, we plan to add non-operating days as well as reducing operation time from double shifts to a single shift from May 12 for some of the plants and production lines producing vehicles for overseas markets.

We sincerely apologize for the inconvenience caused to our suppliers and people in those regions.

Please refer to the below for more details.

Production suspension for nine production lines at five plants (Among a total of 28 production lines at 15 plants)

  • Tsutsumi Plant, production lines #1 and #2
    4 operating days from May 12 (Tue) to 15 (Fri)
  • Tahara Plant, production line #1
    5 operating days from May 12 (Tue) to 18 (Mon)
  • Toyota Motor East Japan, Inc. (TMEJ), production lines F201 and F301 at Higashi-Fuji Plant
    1 operating day on May 12 (Tue)
  • Toyota Motor East Japan, Inc. (TMEJ), production line #1 at Iwate Plant,
    2 operating days for May 12 (Tue) and 13 (Wed)
  • Hino, Hamura Plant, production line #1
    4 operating days from May 12 (Tue) to 15 (Fri)
  • Hino, Hamura Plant, production lines #2 and #4
    1 operating day on May 12 (Tue)

Reduction of operation to a single shift in four production lines at three plants
Tahara Plant, production lines #1 and #3

  • Operation with a single shift from May to June (Employees to continue working double shifts)
  • Hino, Hamura Plant, production line #1
    Operation with a single shift from May to June (No second shift)
  • Gifu Auto Body Co., Ltd., production line #2
    Operation with a single shift from May to June (No second shift)

In addition, since we anticipate that the delivery of some parts from overseas will be affected due to COVID-19, we will halt production for three operating days between April 20 (Mon) and 22 (Wed) for Takaoka Plant production line #2 and Toyota Industries Corporation production lines #301 and #302.

Note that operation plans may change in accordance with changes in demand and the situation of parts delivery, going forward.

Share

Print


Suggested Items

Today’s MilAero Options: Outsourcing—‘Everybody’s Doing it’ Not so True Today

06/27/2016 | Marc Carter
There was a time, not so many decades ago, when that most commonly-stated mantra (“lower labor costs”) behind offshoring printed circuit fab (and some assembly) operations, still had some case-by-case validity.

PartnerTech Inks Framework Agreement with Picadeli AB

04/20/2015 | PartnerTech
PartnerTech and Picadeli AB, a company that currently provides self-service salads in more than a thousand grocery shops in Sweden, have signed a framework agreement regarding the industrialization and manufacture of Picadeli’s unique new refrigerated counter.

Drive a Car? You Can Fly a Typhoon!

02/18/2015 | Pete Starkey, I-Connect007
The EIPC conference delegates see Eurofighter assembly at Airbus Defence and Space. The major attraction was the opportunity to see the final assembly line for Eurofighter Typhoon multi-role combat aircraft destined for the German Air Force. Editor Pete Starkey has a post-show review.



Copyright © 2020 I-Connect007. All rights reserved.